Philippine Policy & Regulation
Supreme Court Voids 2026 Budget Provisions: What Contractors Should Know
A 13–2 ruling dated 7 October 2026 struck down two 2026 unprogrammed-fund provisions and congressional hikes in 2024–2025, with reconsideration being sought. Here is what it means for government contracts.

1What the Supreme Court decided, and when
On 20 October 2026 the Supreme Court publicly announced a decision that reshapes how the national budget may use “unprogrammed appropriations” (UA), the standby spending authority that is released only when specified funding conditions occur. According to The Philippine Star’s 22 October report, the decision is dated 7 October 2026, runs 121 pages, was written by Senior Associate Justice Marvic M.V.F. Leonen for the Court en banc, and was approved by a 13–2 vote. Several justices wrote separate opinions; the Daily Tribune reported that they agreed UA is permissible but differed on how far Congress may amend the President’s budget.
The ruling resolved consolidated petitions against three General Appropriations Acts (GAAs). A legal summary published by Conventus Law identifies them as G.R. Nos. 271059, 271347, E-02472 and E-04036; the lead case, G.R. No. 271059, was filed by the late Representative Edcel Lagman. As reported by GMA News on 20 October, the Court:
- granted Rep. Lagman’s petition and partly granted the petition of former Senator Aquilino “Koko” Pimentel III and others against the 2024 GAA (Republic Act No. 11975);
- granted the petition of Filipinos for Peace, Justice and Progress Movement, Inc. and others against the 2025 GAA (Republic Act No. 12116); and
- partly granted the petition of Representatives Edgar Erice and Leila de Lima against the 2026 GAA.
- ₱449.5 billion
Congressional increase in 2024 UA declared unconstitutional (₱281.9B proposed → ₱731.4B enacted) - ₱17.99 billion
Added to the 2025 DPWH Special Road Fund, struck down - ₱12.75 billion
Increase in certain Special Accounts in the General Fund, struck down under the Administrative Code - 13–2
Reported vote, decision dated 7 October 2026
2The 2026 provisions that were voided, and what survives
The 2026 GAA, Republic Act No. 12314, carries a total budget of ₱6.793 trillion, including about ₱150.9 billion in UA, according to Manila Bulletin’s January 2026 report on the Erice–de Lima petition filed on 8 January 2026. The Court did not invalidate the 2026 GAA as a whole. It struck down Special Provisions 1(a) and 1(b) under Chapter XLIII, the UA chapter, and permanently enjoined the Senate, the House, the Office of the Executive Secretary and the DBM from implementing them (GMA News).
The Daily Tribune describes the two provisions as those authorizing the use of unprogrammed funds on the basis of excess collections or new revenue streams. In the Court’s view, as reported by GMA, the provisions granted the executive overly broad spending authority, breached the limits on total appropriations, partly operated as prohibited lump sums, and “lacked prioritization standards.”
What remains in force matters as much as what fell. The DBM said in a 25 October statement, reported by the Daily Tribune, that “unaffected provisions remain implementable, subject to their respective legal bases, funding conditions and established budgetary procedures.” In particular, releases for foreign-assisted projects rest on a separate funding condition that the Court did not invalidate. Budget Secretary Kim Robert de Leon told a Senate finance subcommittee on 22 October that no funds had been charged against Special Provisions 1(a) and 1(b) for 2026, and that foreign-assisted projects were the only 2026 UA releases so far (GMA News).
The DBM has not published a list of 2026 UA items, projects or peso amounts that it considers affected. As of 6 November 2026, contractors cannot rely on a public schedule and must work from the funding documents for their own contracts.
3The legal basis: four guardrails and the limits on Congress
The Court’s central holding, reported by both GMA News and the Daily Tribune, is that “Unprogrammed Appropriations are not unconstitutional per se.” They are valid only if four conditions are met:
- No lump sums. “In no case shall there be lump sums in Unprogrammed Appropriations.” Congress must identify the purposes and amounts of spending.
- New revenue funds programmed spending first. New income and additional non-tax earnings presumptively support programmed expenditures, unless clear and convincing reasons (such as foreign-assisted projects) justify placing them in UA.
- Prioritization standards. Where a UA item serves more than one purpose, Congress must set sufficient standards for what is funded first if money runs short.
- Within the fiscal program. UA must stay a narrow contingent appropriation consistent with the national fiscal program.
The ruling rests on the constitutional division of budget powers. Article VI, Section 25(1) of the 1987 Constitution bars Congress from increasing the appropriations the President recommends for the operation of the government. According to the Conventus Law summary, the Court held that this ceiling applies to programmed and unprogrammed amounts combined. Congress therefore cannot keep the programmed total within the President’s proposal while moving items into UA and enlarging the overall authority. That is how the 2024 and 2025 increases were found unconstitutional.
The Court also held that the SAGIP item in the 2024 and 2025 UA was a prohibited lump sum. It let the executive identify projects after the budget was enacted, a power the Constitution gives to Congress. GMA quotes the Court calling it a “covert repository of lump sum allocations for DPWH infrastructure like flood control projects.” The Court further held that the bicameral conference committee may only reconcile actual differences between the House and Senate versions, and faulted it for keeping no records explaining its increases and decreases.

4Is the ruling final? The motion for reconsideration and the reactions
No. Supreme Court spokesperson Camille Ting said the decision is “not yet final and executory” (Philstar; Daily Tribune). Under the Rules of Court, a party may move for reconsideration within 15 days from notice. A second motion is generally not allowed. The decision becomes final once that period lapses without a motion or, if a motion is filed, once it is resolved. The Daily Tribune reported that the Office of the Solicitor General (OSG) had until 4 November 2026 to file. As of the research date, we could not confirm from a published report whether the motion was filed or what it argues. Readers should check the Supreme Court docket or the OSG directly.
The executive’s position
On 21 October, Palace Press Officer Undersecretary Claire Castro said the administration “respectfully disagrees” with parts of the ruling and had directed the OSG to seek reconsideration. She argued that requiring total collections to exceed the total revenue target before UA can be used is “an outright alteration of the conditions established by Congress.” In her view, it leaves the mechanism “useless and inoperable for government programs” (GMA News). She also said that, under the operative fact doctrine, there was no basis to hold the President liable, because he was complying with the law.
Solicitor General Darlene Marie Berberabe said on 22 October that the OSG would seek clarification and partial reconsideration. Her focus was the “guardrails prescribed for the exercise of budgetary powers.” She said the OSG was studying whether parts of the decision amount to “judicial overreach,” and that some safeguards may belong to Congress and the executive rather than to the Court (GMA News).
Reactions from lawmakers
As reported by Philstar on 22 October, petitioner Rep. Leila de Lima called the ruling a “significant win” and said UA should be “a standby, not a slush fund.” House Deputy Minority Leader Antonio Tinio suggested that the Ombudsman and COA study how to hold budget authors, proponents and implementors liable. Vice President Sara Duterte said the ruling confirmed her 2024 warnings about the bicameral conference committee. The Palace disputes any suggestion of presidential liability. No court has made findings of liability against any official, and all persons named in these statements are presumed innocent.
5What it means for implementing agencies
The executive’s signals point in slightly different directions. On 22 October, the Solicitor General said the OSG would advise the DBM to hold off on 2026 projects that are clearly covered by the decision but have not yet started. Projects already underway or being implemented in phases should continue. She explained the hold as a good-faith measure: “Iyong mga klaro na sakop doon sa (GAA 2026) decision, huwag muna” (roughly, “Those clearly covered by the 2026 GAA decision, not yet”) (Daily Tribune). In its 25 October statement, the DBM said it “will observe the applicable Supreme Court directives.” It added that it would keep assessing the ruling’s legal, fiscal, technical and operational effects with the OSG. The Tribune’s report also states that the DBM is inclined to follow the ruling while continuing to implement FY 2026 GAA projects (Daily Tribune).
For heads of procuring entities, budget officers and accountants, the practical exposure is personal as well as institutional. The 1987 Administrative Code (Book VI, Sections 46–48) and the Government Auditing Code (Presidential Decree No. 1445) generally prohibit entering into a contract unless an appropriation exists. They require a certification that funds are available, declare non-compliant contracts void, and make the responsible officers liable. Treating an enjoined provision as a valid fund source invites a COA notice of disallowance. Agencies should consider the following steps:
- Map every 2026 UA-funded program, activity and project to its release condition, and separate items released under Special Provisions 1(a)/1(b) from foreign-assisted projects and other unaffected conditions.
- For covered items not yet started, document the decision to defer, and keep the OSG and DBM advice on file.
- Before any new obligation, confirm that the funding document (allotment and cash authority) does not rest on an enjoined provision.
- Preserve procurement records, bid documents and board resolutions. The decision’s criticism of undocumented bicameral changes suggests that the paper trail will matter in audits.
For the wider procurement context, see our overview of public procurement transparency reforms in 2026.

6What it means for contractors and suppliers
Most government contractors will see no direct effect. The decision does not touch programmed appropriations, and the DBM reports no charges against the voided 2026 provisions. Risk is concentrated in a narrower group: suppliers and contractors whose 2026 projects were expected to be funded from UA released on the strength of excess or new revenue. Their position depends on the stage of the contract.
| Contract situation | Likely position as of 6 November 2026 | What to do |
|---|---|---|
| Bid submitted or award pending; funding expected from 2026 UA under Special Provisions 1(a)/1(b) | Most exposed. The OSG has advised holding projects that are clearly covered and not yet started. Awarding requires funds to be certified as available. | Ask the procuring entity in writing to confirm the fund source. Avoid mobilization costs until it is confirmed. |
| Contract signed, work not started | Possible suspension or deferral pending the motion for reconsideration. Whether the contract is valid depends on whether a valid appropriation and funds certification existed when it was signed. | Review the notice-to-proceed, suspension and termination clauses. Keep written instructions from the agency. |
| Work ongoing or phased | The OSG said these should continue. The DBM indicated that implementation continues for unaffected items. | Keep billing records, accomplishment reports and inspection documents in good order. |
| Foreign-assisted project | Funding condition not invalidated, according to the DBM. | Monitor loan or grant agreement compliance as usual. |
| 2024/2025 projects already completed and paid | The operative fact doctrine protects completed, irreversible programs where beneficiaries acted in good faith. The OSG says no refund of spent funds is required. | Keep evidence of good faith and of actual delivery in case of a COA audit. |
Payment and claims
If an agency stops a covered project, a contractor’s remedies depend on the contract and the applicable procurement rules, now principally Republic Act No. 12009 (the New Government Procurement Act) and its implementing rules. Where a contractor has already delivered work or goods that the government accepted and benefited from, Philippine jurisprudence has allowed recovery on a quantum meruit basis even when the underlying contract was defective for lack of appropriation, as in EPG Construction Co. v. Vigilar (G.R. No. 131544, 16 March 2001). Money claims against government agencies generally fall under the primary jurisdiction of the Commission on Audit. Contractors should expect to prove delivery, acceptance and good faith through documents rather than assertion.
If a payment is later disallowed, the Supreme Court’s rules in Madera v. Commission on Audit (G.R. No. 244128, 8 September 2020) govern who must return disallowed amounts. Under those rules, payees who received amounts in good faith in return for services actually rendered are generally treated differently from approving officers who acted in bad faith. These general principles should be checked against each contract’s facts. For disputes that cannot be settled administratively, see our civil litigation practice.
7The 2027 budget: guardrails meet a live bill
The decision arrived while the Senate was reviewing the House-approved 2027 General Appropriations Bill. Senator Panfilo Lacson said on 21 October that the ruling “couldn’t have come at a better time.” He warned that the Senate’s review could restore “hundreds of billions” of pesos in House cuts and realignments, including changes to foreign-assisted projects and added flood control allocations (GMA News). Kabataan Party-list Representative Renee Co, who voted against the House version, alleged on 23 October that it contains UA release triggers and lump sums similar to those the Court struck down. Her allegation has not been tested in court, and no response from House leaders or the DBM to it had been reported.
If the ruling stands, the 2027 bicameral conference committee and the enrolled bill will be measured against the four guardrails. That means no lump sums in UA, prioritization standards for multi-purpose items, combined programmed and unprogrammed totals within the President’s recommendation, and a record explaining bicameral changes. If the OSG’s motion succeeds in narrowing the guardrails, Congress will have more room to decide. For businesses that bid on infrastructure and supply contracts, the practical takeaway is to look at how a project is funded in the 2027 GAA, programmed or unprogrammed, before committing bid and mobilization resources. Our earlier analysis of judicial review of executive action and political developments and business confidence gives further background.

8Key takeaways and next steps
- The Court upheld UA as a mechanism but set four guardrails, and voided specific 2024, 2025 and 2026 items.
- For 2026, only Special Provisions 1(a) and 1(b) of Chapter XLIII were struck down. Foreign-assisted project releases continue.
- The ruling is not yet final, and the executive is seeking partial reconsideration.
- Contractors on unstarted projects funded by covered UA items face the most risk. Confirm fund sources in writing.
- Completed 2024–2025 programs are protected by operative fact where good faith is shown. Individual liability is a separate question.
Companies with government contracts, or with bids pending on 2026 or 2027 projects, may wish to have their funding documents and contract terms reviewed before taking on new costs. Abanto Law Firm assists clients with government contract claims, COA proceedings and related disputes through its corporate law and civil litigation teams. You can contact us to discuss your situation.
9Frequently asked questions
Did the Supreme Court declare the entire 2026 national budget unconstitutional?
No. For the 2026 GAA (Republic Act No. 12314), the Court struck down Special Provisions 1(a) and 1(b) of Chapter XLIII, which govern releases of unprogrammed appropriations based on excess or new revenue, and enjoined their implementation. The rest of the 2026 budget, including programmed appropriations and foreign-assisted project releases, remains in force, according to the DBM.
Is the decision already final?
Not as of the research date. The Supreme Court spokesperson said it is not yet final and executory, and the Solicitor General announced a motion for partial reconsideration. The decision becomes final only after that motion is resolved or the period to file lapses.
Will contractors have to return payments received on 2024 or 2025 projects?
The Court applied the operative fact doctrine to completed, irreversible programs where beneficiaries acted in good faith, and the Solicitor General said the ruling does not require the return of funds already spent. Separate audits or cases may still examine individual transactions, so contractors should keep proof of delivery and good faith.
My 2026 project has been put on hold. What can I claim?
It depends on your contract, whether a valid appropriation and funds certification existed when it was signed, and what work was delivered and accepted. Philippine courts have allowed payment on a quantum meruit basis for work the government accepted. Claims are generally brought before the Commission on Audit, so document every instruction and delivery.
Does the ruling affect the 2027 budget?
Indirectly. If it stands, the 2027 GAA will be measured against the four guardrails on unprogrammed appropriations. Lawmakers have cited the ruling during the Senate’s review of the 2027 budget bill, and some allege the House version repeats the features that were struck down. Those claims remain contested.
Sources and references
- SC strikes down 2024, 2025 budgets, sets limits for unprogrammed appropriations — GMA News Online (2026-10-20)
- High Court voids ₱449.5-B unprogrammed funds hike — Daily Tribune (2026-10-20)
- SC upholds unprogrammed funds, strikes down unconstitutional budget increases — Daily Tribune (2026-10-21)
- Malacañang asks SC to revisit ruling on 2024, 2025 national budgets — GMA News Online (2026-10-21)
- Lacson: SC ruling on past budgets timely as Senate reviews 2027 spending plan — GMA News Online (2026-10-21)
- Palace to appeal SC ruling on budget — The Philippine Star (2026-10-22)
- SolGen to seek partial reconsideration of SC ruling on past budgets — GMA News Online (2026-10-22)
- OSG advises DBM to halt affected 2026 budget projects after SC ruling — Daily Tribune (2026-10-22)
- DBM: No funds released under unconstitutional provisions of 2026 budget — GMA News Online (2026-10-22)
- Unaffected budget provisions remain workable — DBM — Daily Tribune (2026-10-25)
- SC sets deliberation on petition vs ₱150-B unprogrammed appropriations in 2026 national budget — Manila Bulletin (2026-01-13)
- Supreme Court ruling on unprogrammed appropriations (Pimentel III v. Bersamin and related cases) — summary — Conventus Law
This article is for general informational purposes only and does not constitute legal advice. Laws, regulations, and regulatory requirements may change, and reading this article does not create an attorney-client relationship with Abanto Law Firm. Readers should consult qualified Philippine legal counsel regarding their specific circumstances.